π€ Project Timelines and Application Process
This page outlines the process for starting projects in Tech Fleet.
The Project Phase Timelines
Tech Fleet project team training involves a lot of people and a lot of parts. This page outlines the steps involved before a project phase begins, during the phase kickoff, during the project phase, and in between project phases.
Diagram of the Project Lifecycle in Tech Fleet
Here's a diagram of the steps in the Tech Fleet project lifecycle:

Before the Project Phase Begins
Duration
6 weeks
Steps
- Tech Fleet meets with client to collect needs. 
- Client and Tech Fleet agree to desired scope and deliverables. 
- Tech Fleet determines project roles that are needed for the project. 
- Tech Fleet project coordinator creates applications. 
- Tech Fleet opens applications to the community for 5 days. 
- Applications close. 
- Co-leads who apply get interviewed by the project coordinator. 
- Co-leads are selected. 
- Co-leads review apprentice applications from the General and Project Phase applications to choose their interviewees based on who has applied. 
- Co-leads reach out and schedule up to 10 interviews per team with potential apprentices who've applied. 
- Co-leads pick up to 4 apprentices per team position from those they've interviewed. 
- Team does ice breakers. 
- Team starts the Pre-Kickoff for 2 weeks. 
- Project sprint kicks off for 8 weeks. 
- After the 8 weeks of work, the team gets together and compiles hand-off for 1 week. 
Project Phase Pre-Kickoff
Duration
3 weeks
Steps
- The team does ice breakers together 
- The Agile coach works with the team to discuss Service Leadership and Agile Philosophies in team work 
- The Agile coach works with the team to discuss how to resolve team conflict 
- The Agile coach works with the team to produce the following for kickoff: - Client kickoff meeting 
- Project goals and deliverables 
- A team working agreement 
- Team roles and responsibilities (called a RACI chart) 
- A sprint plan for all teams to map out work 
- Access to Notion project repository, Discord channels, and meeting link scheduling 
- A backlog of work items based on the sprint plan 
 
During the Project Phase 
Duration
8 weeks
Steps
- Each sprint, the team progresses on work and demonstrates their progress in sprint demos. 
- Each sprint, the team adjusts their sprint plans and backlog based on collaborations with the client and user. 
- Each sprint, the project managers fill out a progress check-in to identify how their team is doing. 
- Before the current project begins, the Tech Fleet Board will start the process of planning the next phase of work with the client and the team. 
- Current team mates who are interested in re-applying provide their interests with the project coordinator. 
- The next phase of the project is anticipated to open during or right after the previous phase so that current teams have a chance to meet with new teams and discuss their progress together. 
Project Hand-off Week
Duration
1 week
Steps
- The team documents their hand-off based on the Notion template provided to them. 
- The team holds a final retrospective to reflect on their work and how it went. 
- The team works with Agile coaches and project coordinators to discuss how they will tell their story of the project work within their upcoming case study. 
In-Between Project Phases
Duration
Ongoing
Steps
- The Tech Fleet Board, project coordinators, and the client keep in touch about the progress of the project work. 
- The project coordinators update the project dashboard information from the work in the latest phase. 
- The Tech Fleet Board and project coordinators work together to ensure people have what they need to compile their case studies. 